MVA - Spittelau |
SCR-DeNox-plant |
Austria |
Preparation of commissioning documentation |
2013 2014 |
||||
Erection documentation |
Power station projects |
Germany |
As-Built-documentation, isometrics, material documentation |
2013 |
||||
Waste incineration |
District heating |
Austria |
Project execution, procurement management, plant documentation, ROHR2 analysis |
2013 |
||||
Waste incineration |
Waste incineration |
Turkey |
CAD plant layout |
2013 |
||||
Various projects |
Boiler plants |
Worldwide |
Piping engineering, basic engineering for steel structure, detail engineering |
2013 |
||||
District heating station |
Judenburg |
Austria |
3D plant and piping engineering, As-Built-documentation |
2013 |
||||
SCR |
VOEST |
Austria |
Expediting, site supervision |
2011 |
||||
GDK |
Water and steam system |
Austria |
Project management |
2010 |
||||
GDK |
SCR |
Austria |
Shop drawings for SCR injection |
2009 |
||||
Long distance steam line |
Chemical works, waste incineration |
Switzerland |
Technical project management |
2009 |
||||
Waste incineration |
Flue gas purification |
Austria |
Detail engineering PDMS, 2D shop drawings, secondary supports |
2009 |
||||
Waste incineration |
Flue gas purification |
Austria |
Project execution, deputy project manager |
2009 |
||||